Supplier Defect Report - verification of actions and closing

Once the 4D section of the SDR is completed and verified by Bobcat Quality (there will be Yes next to the word Verified) an email will be sent to the choosen contacts in the Supplier record.

The SDR can be once again edited by clicking the detail.

Verified Actions

4D

The 4D section must be Verified by Bobcat Quality. The verification means Bobcat is satisfied with the RC details provided by Supplier. If Supplier doesn't respond in time to the SDR Bobcat might choose to scrap the defective parts. In this case the actual date when the parts were scrapped will be filled in the Send/Scrap field.

If Supplier requests the parts to be sent back for analysis of Root Cause, the field Send/Scrap, Shipping cost, and Tracking # will also be populated by Bobcat with the relevant data.

5D - 8D

Once the 5D - 8D sections are filled by supplier in due time all will be Verified by Bobcat Quality. The verification is a mark that Bobcat is satisfied with Supplier actions described in each section.

Invoicing the SDR

Once the Root Cause for the described defect is established and Verified by Bobcat Quality the corresponding cost of the entire SDR can be either invoiced to Supplier or the SDR cancelled.

In the case of invoicing Bobcat Quality (SQE) will progress the SDR from Submitted status to Billing status. At this phase the SDR is handled by Bobcat Accounting and an invoice for the Total cost is issued to the Supplier. Bobcat Accounting will then progress the SDR from Billing status to Invoiced status. An automated email will be sent to Supplier to inform about the change.

In the case when Supplier doesn't respond to the email notifications and doesn't provide the required information within the indicated time limits, Bobcat Quality will progress the SDR for invoicing regardless.

In the email Supplier will find the invoice number and the amount that is invoiced. The Supplier might choose to send credit note for the specified sum with the SDR reference.

Closing the SDR

The SDR can be closed by Bobcat Quality only after all Supplier corrective actions have been verified. To close the SDR Bobcat Quality (SQE) will progress the SDR from Invoiced to Closed status. The SDR will remain visible on the Supplier portal, but no further edits will be possible to the SDR.

Cancelling the SDR